DeSoto HIGH SCHOOL
DeSoto, KS
![20150611_081543.jpg](https://static.wixstatic.com/media/d809a4_8a6e36d26d0647719d5700724f1d0b95~mv2_d_4128_2322_s_2.jpg/v1/crop/x_232,y_0,w_3474,h_2322/fill/w_576,h_348,al_c,q_80,usm_0.66_1.00_0.01,enc_auto/20150611_081543.jpg)
Contractor Foundation Recovery Systems.
Project Details:
This project consisted of a foundation shoring along a 56 foot long section of a stepped concrete foundation with a masonry wall above to allow for excavation for construction of a basement addition to the high school.
The design incorporated 14 push piers 11 helical lateral restraints and a 350 sq.ft reinforced shotcrete wall with 23 helical soil nails.
![20150609_114410.jpg](https://static.wixstatic.com/media/d809a4_83df0f0e435f4b63bb5fa8aaca40c2b4~mv2_d_4128_2322_s_2.jpg/v1/crop/x_903,y_0,w_2322,h_2322/fill/w_359,h_329,al_c,q_80,usm_0.66_1.00_0.01,enc_auto/20150609_114410.jpg)
![20150603_094408.jpg](https://static.wixstatic.com/media/d809a4_5fa4b643e9d841c39a6dd0ccd68a1f4f~mv2_d_2322_4128_s_2.jpg/v1/crop/x_0,y_2313,w_2322,h_1542/fill/w_545,h_324,al_c,q_80,usm_0.66_1.00_0.01,enc_auto/20150603_094408.jpg)
![logo.png](https://static.wixstatic.com/media/d809a4_b9f359734ba041dfa0ac41bb2436db77~mv2.png/v1/fill/w_190,h_131,al_c,q_85,usm_0.66_1.00_0.01,enc_auto/logo.png)
bottom of page